| This page provides current construction information and target dates for college facilities. It was last updated Jan-12-2009, R. Kurtz |
|
 |
Untitled Document
Life Sciences Building Renovations /Repairs
| Job |
|
|
Done |
| Fac Serv. meet with Bret Elderd, renov estimate promised |
12/9/08 |
12/9/08 |
• |
| 09-394854 Room 223 estimate to be provided |
|
|
|
| 09-422308 Room 232 estimate to be provided |
12/19/08 |
|
|
| Room A725 HVAC and plumbing design to be done |
tba |
|
|
Meet with Fac Serv RE Brent Christner Freezer Problem
-appears to be refrigerant issue
|
|
12/16/08 |
• |
| Eagle Refrigeration to be contacted |
12/16/08 |
|
|
| Floor in 631 repair: Feb-Apr fish will be out of site |
3/1/09 |
|
|
In addition to ongoing repairs, there will be a significant waterproofing of the LSA that will occur. On 12/22/08 representatives from the College (Newcomer, Ball, Kurtz) LSU Systems (Howell), LSU Facility Services (Favaloro, Territo, Kojis) met with Ken Johnstone of State Roofing and Waterproofing. Estimated dates are provided below.
Life Sciences Waterproofing
| Job |
|
|
Done |
| Meet with Ken Johnstone, State Roofing, view problem |
12/22/08 |
12/22/08 |
• |
| Develop "Program" |
|
1/23/08 |
|
| Develop "Design Process" |
tba |
|
|
| Establish "Scope" |
tba |
|
|
Establish time-frame for funding and repair
|
|
|
|
|
|
 |
Untitled Document
Choppin Annex Timetable
| Job |
|
|
Done |
| Meeting with Architects in Systems Office |
|
|
• |
| Meeting with Architects in Systems Office |
|
|
• |
| Architect to Draw New Elevation (2 wks?) |
8/6/2008 |
9/10/2008 |
• |
| Program Received |
8/11/2008 |
9/10/2008 |
• |
| Comments from Chem/BASC provided |
9/12/2008 |
|
• |
| Contract Amendment / Project refinement (30 days) |
9/15/2008 |
10/31/2008 |
• |
| Meet with Lab Layout Expert (Karlsberger) |
12/2/2008 |
12/2/2008 |
• |
| Delivery/Finalize Lab Layout (Karlsberger - 14 days) |
12/2/2008 |
12/16/2008 |
• |
| Meet sched. to Finalize Lab Layout w/ Karlsberger |
1/8/2009 |
1/8/2009 |
• |
| Design Documents (60 days) – – next target date |
|
1/31/2009 |
|
| Engineering Calculations (Assaf wants April deadline) |
1/31/2009 |
4/1/2009 |
|
| Construction Documents (60 days) (June 12 in contract) |
|
5/1/2009 |
|
| Final Reviews (30 days) |
|
2/20/2008 |
|
| Bid (60-75 days) |
2/23/2008 |
5/01/2008 |
|
| Begin Construction |
5/1/2009 |
|
|
|
|
 |
Untitled Document
Field Camp Deferred Maintenance Job List
| Job |
|
|
Done |
| Rewire buildings and transmission lines in Upper Camp and Broadmoor |
|
|
|
| Kitchen repairs: grease trap, prep sink, prep counter |
|
|
|
| Replace water filtration system |
|
|
|
| Re-roof Staff cabin in upper camp and two cabins in lower camp |
tbd |
|
|
|
|
 |
Untitled Document
Hatcher Hall Renovation Timetable Plan C
| Job |
|
|
Done |
| Meeting with Facility Services to Discuss Plan |
|
|
• |
| Meeting with Facility Services at Hatcher 10:00 am |
|
|
• |
| Meet with Vellupillai to discuss Hatcher Space |
12/18/2008 |
|
• |
| Meet with Fac. Serv. to discuss renovations |
1/14/2009 |
|
|
| Music moves |
|
|
|
| 2nd Fl. N vacated/paint & service for IP |
7/1/09 |
8/1/09 |
|
| 2nd Fl. N occupied by International Programs |
8/1/09 |
|
|
| LSYOU vacates Hatcher 1st Fl. S offices paint&Service |
9/7/09 |
|
|
| S. Office wing occupied |
10/1/09 |
|
|
| Dean's office Renovate #2 |
|
|
|
| Interior Space Renovate #3 |
|
|
|
| |
|
|
|
*These dates are are from incomplete notes - if you have better data, please forward.
Hatcher Hall Timeline from Emmett David
| Job |
|
| PM60 approval for designer |
|
| Designer contracting through Purchasing and State Contractual Review |
|
| Bid documents preparation and permitting |
100 days |
| Coordination and approval |
10 days
|
| Bidding and award |
45 days |
| Construction |
120 days |
| Fire Marshal inspection and occupancy |
10 days |
| TOTAL |
335 days |
*These durations are are from Emmett David Oct. 15, 2008.
|
|
 |
Untitled Document
South Campus Greenhouse
Ahead of Schedule!
| Job |
|
|
Done |
| Install Culvert |
|
11/06/2008
|
• |
| Install Gravel Drive |
11/07/2008 |
11/12/2008 |
• |
| Tie-in to Existing Electrical |
11/13/2008 |
11/17/2008 |
• |
| Set New Transformer |
11/18/2008 |
11/19/2008 |
• |
| Pour Foundation |
11/20/2008 |
11/26/2008 |
• |
| Install Plumbing Outside Foundation |
11/27/2008 |
12/01/2008 |
• |
| Install Waterlines Inside |
12/02/2008 |
12/04/2008 |
• |
| Install Gravel Building Pad |
12/05/2008 |
12/09/2008 |
• |
| Erect Greenhouse |
12/10/2008 |
12/23/2008 |
• |
| Interior Electrical |
12/24/2008 |
01/08/2009 |
|
| Install Propane Tank |
01/09/2009 |
01/12/2009 |
|
| Install Fencing |
01/13/2009 |
01/19/2009 |
|
| Punch List Items |
01/20/2009 |
01/22/2009 |
|
| Job Turnover |
|
01/23/2009 |
|
Timetable provided by Allen Westerchil, Block Construction.
|
|
 |
Untitled Document
Herbarium Repair Timetable
| Job |
|
|
Done |
| Carpet Squares purchase order released |
|
10/28/08 |
• |
| Carpet received |
|
11/3/08 |
• |
| Repair by Automated Storage & Retrieval, L.L.C. |
|
11/14/08 |
• |
|
|